Subject to God’s will and timing, below represents the progress for completing the property purchase with estimated dates.

Letter of Intent (March 2025):
Complete
-
Sent letter of Intent to purchase new property for the Church.

Contract Signed (June 2025):
Complete
-
Completed paperwork and signed contract to purchase new property for the Church.

Fundraising and Financing:
Continuous
-
Fundraising and financing for new property and renovations including Church items (Iconostasis, Altar, flooring etc). Click here for ways to donate.

Due Diligence Period (June 2025-Septemeber 2025):
In Progress
-
Ensuring property is up to code and ready to be used.

Official Closing (October 2025):
Not Started
-
Officially closing on the property and making it home to David the Prophet and St. Karas Coptic Orthodox Church!
ESTIMATED CHURCH OPENING - DECEMBER 2025